Catch-up Plans
Procurement process for road concreting delayed by 21 days due to incomplete technical specifications
Actions: BAC re-issued bid documents with complete specs; re-published on February 5. Conduct pre-bid conference to clarify requirements.
Target: 4/15/2026
Bid deadline extended by 16 days due to failed bidding (no complying bidders on first call)
Actions: BAC coordinated with contractors association to increase participation. Second bidding completed April 5 with 3 complying bids. Currently evaluating.
Target: 4/20/2026
Q1 fuel budget utilization at 18% against 25% target due to delayed delivery of gasoline
Actions: Coordinated with supplier for priority delivery. Bulk purchase order processed March 15. Q1 backlog absorbed in Q2 procurement.
Target: 3/31/2026